Pure Aqua supplied a complete water treatment system for a bottling company in Algeria, complete with microprocessor control panel, high rejection membranes, feed TDS 7,000 ppm;
LOCATION: Algeria, Algeria
Date : December 2004
Capacity: 130,000 GPD |
|
 |
Pure Aqua supplied a BWRO to The Royal Family in Qatar, complete with pre-treatment and chemical dosing system;
LOCATION: Doha, Qatar
Date: December 2004
Capacity: 43,200 GPD |
|
 |
Pure Aqua supplied SWRO for Aysir Construction and Tourism Resort; system consists of 2 trains of 200m3/day each, complete with touch panel PLC control panel, pre-treatment, cleaning skids, chemical dosing, and energy recovery turbine.
LOCATION: Istanbul, Turkey
Date : November 2004 |
|
 |
Pure Aqua supplied an industrial BWRO system for Pepsi Cola Co.; capacity is 43,200 GPD with pre-treatment, pre-chemical dosing system, and microprocessor control panel
LOCATION: Lima, Peru
Date: October 2004 |
|
 |
Pure Aqua supplied a complete water treatment system for a bottling company in Yemen, complete with RO pre-treatment and UV system;
LOCATION: Sana'a, Yemen
Date :September 2004
Capacity : 11,000 GPD
|
|
 |
Pure Aqua supplied a fully skid mounted, pre-piped, pre-wired, 3 step filtration process complete with touch panel PLC control panel, and chemical dosing systems for Alto Chicama Mine Project-Camp 4; capacity is 48 GPM
LOCATION: Alto Chicama, Peru
Date: August 2004 |
|
 |
Pure Aqua supplied an industrial BWRO system for an oil lube manufacturer; capacity is 110,000 GPD with pre-chemical dosing systems, cleaning skid, and microprocessor control panel.
LOCATION: Shuweikh, Kuwait
Date: July 2004 |
|
 |
Pure Aqua supplied an industrial BWRO system for Sugar Factory in Pakistan; capacity is 225,000 GPD with pre-chemical dosing system and microprocessor control panel
LOCATION: Jhang, Pakistan
Date : July 2004 |
|
 |
Pure Aqua supplied a SWRO system for Metito International in UAE; system included high rejection membranes, microprocessor control panel, and plunger type high pressure pump;
LOCATION: Sharajah, UAE
Date: July 2004
Capacity: 11,500 GPD |
|
 |
Pure Aqua supplied a two-train industrial BWRO system for NVE Pharmaceutical Factory in New Jersey-USA; capacity is 160,000 GPD with pre-chemical dosing system and membrane cleaning skid
LOCATION: New Jersey, USA
Date: June 2004 |
|
 |
Pure Aqua supplied a fully skid mounted, pre-piped,pre-wired, 3 step filtration process completewith clarifier, touch panel PLC controlpanel, and chemical dosing systems for AltoChicama Mine Project-Camp 1 & 2;
LOCATION: Alto Chicama, Peru
Date: May 2004
Capacity: GPM |
|
 |
Pure AquaSupplied Brackish Water RO to Pure OTech California-USA, this system to beused for irrigation in NorthernCalifornia, capacity: 30,000 GPD withall pre and post treatment systems andmicroprocessor control panel
Location: California, USA.
Date: April 2004 |
|
 |
Pure Aqua participatesin the 2004 WQA Water Quality AssociationConvention.
Location: Baltimore, Maryland USA.
Date: March 2004 |
|
 |
Pure Aqua Supplied BrackishWater RO to EEPSA Power plant in Lima Peru,72,000 GPD with all pre and post treatmentsystems and cleaning skid.
Location: Lima, Peru.
Date: March 2004 |
|
 |
Pure Aqua Supplied BrackishWater RO to a major water treatment wholesalecompany in Dubai 43,000 GPD with all instrumentationsand microprocessor control panel.
Location: Dubai, UAE.
Date: February 2004 |
|
 |
Pure Aqua Supplied acomplete reverse osmosis and filtration systemfor Universal Robina Company in the PhilippinesIslands, 200,000 GPD
Location: Manila, Philippines.
date: January 2004 |
|
|